Hyperscale Data Says Michigan AI Data Center Needs $74.8M More, Flags Going-Concern Doubt

Hyperscale Data said its Michigan AI data center project will require another $74.8 million between November 2026 and March 2027, and warned in a regulatory filing that existing cash and available financing are insufficient to cover planned spending and obligations over the next 12 months, raising substantial doubt about its ability to continue as a going concern. The company held $17 million in unrestricted cash against $231 million in current liabilities at the end of September, and has sold about 1,113 BTC for roughly $74 million since late July.